All this work complies with specifications and standards laid out in the latest permanent way instruction book of 2012 and the track welding book of 2007


Track Siding and Yard Maintenance

Incoming line RHS drain completed

*

Incoming line RHS drain requried

*

Installation of new stop block

*


Check and inspect all Rail condition for overlaps, cracks and loose fastenings.
Any damaged rail is reported for Rail Repairs.
Check cant and alignment and correct as required.
Check for slacks and mud-holes and repairs.
Ensure adequate drainage alongside track at correct distance from track.
Ensure 50mm gap below rail and rail is not enclosed in sand/ stones to minimize rust.
Remove any obstructions on track including overhanging vegetation and ensure visibility for train operator.



New Siding Stop Boards

*

Old entrance siding stop board

*

Painting turnout and tumbler

*

Slewing and alighnment of track

*

Old exit Siding Stop Board

*